meta data for this page
Differences
This shows you the differences between two versions of the page.
| Both sides previous revisionPrevious revisionNext revision | Previous revision | ||
| java2012:grp3:start [2012/10/19 01:30] – [Conclusion] poorang | java2012:grp3:start [2012/11/01 13:13] (current) – [Final Report] nikos | ||
|---|---|---|---|
| Line 8: | Line 8: | ||
| After we received the requirement, | After we received the requirement, | ||
| ====== Scrum status====== | ====== Scrum status====== | ||
| - | | + | |
| - | ** Product Backlog | + | ===== Product Backlog |
| - | * User stories | + | |
| {{: | {{: | ||
| Line 16: | Line 15: | ||
| {{: | {{: | ||
| - | **Sprint Backlog | + | ===== Sprint Backlog |
| - | *What we planned and managed to do | + | === What we planned and managed to do === |
| {{: | {{: | ||
| - | | + | More precisely, the following elements were implemented: |
| + | |||
| + | | ||
| + | * User, UserRole, Forecast, Activity, Week, Client, Login | ||
| + | * Controller Classes | ||
| + | * UserController, | ||
| + | * Views | ||
| + | * Appropriate views for the aforementioned classes. | ||
| + | * Login Functionality | ||
| + | * The controllers and views were coded so that they support login functionality. | ||
| + | |||
| + | === BurnDown Chart === | ||
| {{: | {{: | ||
| - | *What we couldn' | + | ===== What we couldn' |
| - | Due to lack of time and knowledge of the used framework and tools, we didn't manage to complete the following tasks: | + | Due to lack of time and knowledge of the used framework and tools, we didn't manage to complete the following tasks (the unimplemented tasks are shifted to sprints 2 and 3): |
| {{: | {{: | ||
| ===== Screenshots ===== | ===== Screenshots ===== | ||
| **Data base** | **Data base** | ||
| - | * {{database_model.jpg?400|}} | + | |
| + | {{: | ||
| **Application** | **Application** | ||
| - | Coming soon.... | + | {{: |
| - | + | {{: | |
| + | {{: | ||
| + | {{: | ||
| + | {{: | ||
| ===== Code ===== | ===== Code ===== | ||
| **Upload and attach the .war package for final delivery** | **Upload and attach the .war package for final delivery** | ||
| Line 47: | Line 60: | ||
| * Use .zip format | * Use .zip format | ||
| | | ||
| + | {{: | ||
| + | |||
| + | ===== Final Report ===== | ||
| + | {{: | ||
| + | |||
| ===== Conclusion ===== | ===== Conclusion ===== | ||
| ** What was delivered, how ** | ** What was delivered, how ** | ||
| - | coming soon... | + | - Source code of the final application |
| + | - Documentation on this wiki including: | ||
| + | - Product Backlog | ||
| + | - Sprint Backlog | ||
| + | - BurnDown chart | ||
| + | - Database model | ||
| ** Our experiences on code camp ** | ** Our experiences on code camp ** | ||